City of Edinburgh Council announce road resurfacing programme for Summer 2019

City of Edinburgh Council have announced that a series of streets in the Leith area will be resurfaced over coming weeks.

The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.

The resurfacing works are planned to start on 27th May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.

Listed below are the streets affected along with the proposed month/order of the works and traffic management. Please note this is subject to change following final confirmation from the contractor (MacLay Civil Engineering) next week. Neighbourhood notification letters will be issued to local residents and traders prior to the commencement of each phase.

Street

Month

Treatment

Proposed Traffic Mgmt

Abercromby Place

May

Fully Resurfaced

Road closure. Local diversion

North Leith Sands

May

Fully Resurfaced

Road closure. Local diversion

Albany Street

June

Fully Resurfaced

Road closure. Local diversion

Lindsay Road

June

Fully Resurfaced from North Leith Sands to Portland Street

One-way closure. Local diversion

Broughton Street

June

Full Resurfaced

Northbound Road Closure

Ocean Drive

June

Fully Resurface both northbound lanes from Lindsay Road to roundabout, and southbound bus stop at Holiday Inn

Road closure. Local diversion

East London Street

June

Fully resurface from roundabout to Cochran Terrace

Lane closures

Annandale Street

June

Fully resurface from Haddington Place to roundabout and from roundabout to Hopetoun Street

Road closure in 3 phases. Local diversion

Great Junction Street

June

Fully resurface from Cables Wynd to Henderson Street

Lane closures or Eastbound closure with local diversion

Dalmeny Street

July

Overlay setts in centre of carriageway (retain setts in parking areas)

Road closure. Local diversion

Hopetoun Street

July

Various sections resurfaced

full Road closure. Local diversion

Gordon Street

July

Fully resurfaced and overlay setts on Manderston Street

Road closure. Local diversion

McDonald Road

July

Resurface eastbound bus stop at Papermill Wynd

Lane closure or southbound closure with local diversion

Broughton Road

July

Fully resurfaced from Broughton Primary to Bonnington Road

Road closure in 2 phases. Local diversion

Links Place

July

Fully resurfaced

Road closure. Local diversion

Duncan Place

July

Fully resurfaced

Road closure. Local diversion

Bonnington Road

July

Fully resurfaced from Broughton Road to Corunna Place

Road closure in 3 phases. Local diversion

Academy Street

July

Overlay setts in running lanes (retain setts in parking areas)

Road closure. Local diversion

Newhaven Road

August

Fully resurfaced from Pilrig Street to Pitt Street

Road closure in 2 phases. Local diversion

East Hermitage / Restalrig Rd Junction

August

Fully resurface Junction area

Temporary Traffic Lights and closure of Links Gardens. Local Diversion

Duke Street / Easter Road Junction

August

Fully resurface roundabout and approaches

Temporary traffic lights

Pilrig Street

August

Fully resurfaced from Spey Street to Newhaven Road

Road closure in 2 phases. Local diversion

Easter Road

August

Various sections resurfaced

Various lane closures and temporary traffic lights. Possible road closure required at Albion Road with local diversion

Scheme of Administration for Community Councils, review by City of Edinburgh Council – final phase

You will recall previous posts which detailed the review of the Scheme of Administration for Community Councils in Edinburgh.

 

Today, City of Edinburgh Council have launched another consultation on proposed changes to the scheme.

 

 

(The below text is copied from the City of Edinburgh Council website)

Overview

On 7 February 2019, the Council authorised the Review of the Scheme for Community Councils. Minor changes were made and approved for further consultation on 2 May 2019.

The Scheme, Constitution and Standing Orders set out the rules and regulations governing community councils including election procedures, meeting arrangements, membership, financial provisions and a code of conduct.

The review aims to improve and update the terms and provisions of the Community Council Scheme. A complaints procedure is also proposed for considering breaches of the code of conduct.

Your views are welcome on the draft Scheme and complaints procedure as contained within the Full Council report.

Your opinion matters

The consultation period runs until 3 June 2019.  You can send your comments by

Please include your name, address and postcode.  No personal details will be published.

Further information about community councils and the review is available at on the Council website

ParkLife Project: Leith Links update

An update on the Edinburgh ParkLife project in relation to Leith Links…

Introduction

Parks are vibrant public spaces that are important for local communities as places to exercise, relax, play and appreciate nature. The ParkLife project, a partnership between the University of Edinburgh and the City of Edinburgh Council, is exploring how technology can help gather more information about how parks are being used and enjoyed – by wildlife and people – to help those who manage and care for them.

The project ran four community meetings across Edinburgh, including one in Leith organised by Leith Links Community Council, to find out what members of the community want to see improved in their park, what the main challenges are, and which areas are the most/least used in their park. Taking this forward, we then asked them to think about the role that technology might play in all these issues.

Leith Links

Our Leith workshop took place at the beginning of April, was hosted by the Leith Links Community Council in Leith Community Centre and was attended by fifteen Leithers. We divided the attendees into three groups and seated them around an enormous map of Leith Links. We were also lucky to have Scott Thomson in attendance – Scott is the Park Officer for Leith Links.

We then asked them to quickly list everything happening in the Links and to mark their location with a coloured dot on the map. Green dots represent the most used areas, red dots mark areas of conflict and yellow dots specify areas for potential opportunities. As you can see in the photos, the attendees identified up to twenty areas, with the space around the playground being the most colourful on all three maps.

After this exercise, everyone came together to walk around each table to discuss the outcomes. The sorts of issues raised included dog owners using designated play areas and the football pitches; the lack of seating in the playground; and whether it was fair for military fitness groups to use the Links without contributing towards its upkeep. There were lots of opportunities to improve the park: planting a community garden and the improvement of the allotments; the need for better cycle path connections; the restoration of the bowling greens; and a wish for an ice-cream stand, to name a few.

For our last activity, we asked the attendees to narrow down their thoughts to name ONE opportunity to be created or ONE challenge to be solved. They produced the following list:

1. Using social media to canvass views on how the bowling green can be restored.

2. Improving the infrastructure of the non-sporting spaces e.g. picnics or BBQs.

3. Surveying how many people use the park and what people are doing in different areas.

Understandably, funding was the single most important obstacle mentioned by the attendees. The ParkLife team will be to take this list and see how using technology can help. This technology won’t replace getting out Leith Links and speaking to more people. Amongst other things, it is hoped that new information will provide more evidence to make the case for more funding for Leith Links.

The workshops were our first steps to talk with the local communities around Leith Links and other areas across Edinburgh. They reinforced how vibrant and integral these public spaces are for those who use and live near them. We look forward to working with the communities and seeing how parks across Edinburgh bloom over Spring and Summer.

We would like to thank all the participants who attended our workshops and shared their insights. If you want to find out more about ParkLife then you can contact us at parklife@ed.ac.uk or visit our website https://www.edinburghlivinglab.org/projects/parklife

ParkLife Project Seeking Community Volunteers (Leith Links)

You’ll recall that earlier this year we brought you news of the Edinburgh ParkLife project, which is seeking to use data & information to improve Leith Links (and three other parks elsewhere in the City).

They are moving forward with their project and require the assistance of some volunteers to help them.

 

 


The ParkLife user research team invites you to be a ‘park blitz’ volunteer. With your help, we will conduct short face-to-face surveys with park users about their experiences in four parks across Edinburgh. ‘Blitzes’ will last for two hours in one park, and volunteers can opt to participate in more than one blitz. We havefurther opportunities to volunteer at two park community events, for two or four hours per event. You will receive a short trainingsession on the survey questionnaire on 7 May at 2pm (if unavailable then, please let us know).

User research is part of the larger ParkLife project, which experiments with new techniques for gathering and analysing park data. For more information go here.

We will provide a packed lunch and refreshments.

Please indicate your availability in the doodle poll below:

https://doodle.com/poll/f8q3rsnpk9b9uuar

The ParkLife user research team is excited to meet all of you!

Morgan & Michaela

Morgan.currie@ed.ac.uk and M.Hubmann@ed.ac.uk


 

Scottish Government consultation on Short Term Lets

Our Leith community has raised many concerns over recent months regarding the effect of Short Term Lets in our area.

The Scottish Government has this week launched a consultation asking for your views in relation to such usage of property.  You have until 19 July 2019 to submit your views.

 

 

Leith Links Community Council election 2019 | provisional timetable announced

City of Edinburgh Council has announced the provisional timetable for the upcoming Leith Links Community Council elections, with voting day expected to take place on 31 October 2019.

Event

Day

Provisional timeline

Notice of Election (start of nomination period)

-52

9 September

Close of Nominations (forms to Returning Officer)

-31 4pm

30 September

Withdrawal of Nominations

-31 4pm

30 September

Notice of Poll (if required)

-21

10 October

Polling Day

0

31 October

 

You may recall that in 2016 Leith Links Community Council was the only Community Council in Edinburgh to be elected by public vote, when seventeen members of community stood for election to our body of 12 Community Councillors.

Between now and the election period we will doing all we can to encourage & support people to stand as candidates, and should we require a public vote we will be doing as much as possible to get as many voters as possible to cast their votes. In 2016 588 voters had their say, this represented 6.9% of eligible voters.

Work begins on new Leith Links play park

Leith Links Community Council is pleased to note that work has now began on site as part of the new Leith Links play park.

The new play park is expected to be open by the end of July 2019.

 

Reporting noise nuisance from Seafield Waste Water Treatment Plant

A number of months ago we introduced one handy web from on our website which allowed members of our community to report nuisance & intrusive odours from Seafield Waste Water Treatment Plan to City of Edinburgh Council, Scottish Water, Veolia, Scottish Government and the Scottish Parliament.

As we have recently received a significant number of complaints relating to nuisance noise from the plant, we have updated our form, allowing you to report smell and / or noise from the plant.

The form can be accessed by clicking here, and can be used any time, any day.

 

 

Strengthening Community Councils: Exploring how community councils can contribute to democratic renewal in Scotland.

This report from SCDC and What Works Scotland explores how community councils can be even more relevant in Scotland’s evolving policy context, especially as public service reform continues through the Local Governance Review.

The report is over 80 pages in length but of particular interest to you may be the recommendations, which are detailed on page 4.

To view the report follow this link.

 

Leith Links Community Council Meeting, 29 April, 6:30pm, Leith Community Centre

The next meeting of the Leith Links Community Council will be on Monday 29th April , at 6:30pm in the Leith Community Education Centre, New Kirkgate.

If you live in the area, you are warmly welcomed to attend.

Please find the Agenda for the next meeting here Agenda29.4.19

and minutes of our March meeting  Monday 25 March 2019

 

 

 

1 4 5 6 7 8 9