City of Edinburgh Council announce road resurfacing programme for Summer 2019

City of Edinburgh Council have announced that a series of streets in the Leith area will be resurfaced over coming weeks.

The roads affected have been prioritised because of their current condition and because the upcoming tram works will prevent any planned resurfacing work from taking place in and around the proposed tram line during the construction period.

The resurfacing works are planned to start on 27th May and will be carried out during weekdays in separate phases in order to minimise disruption to the public. On some traffic sensitive routes, work may be carried out under nightshift to minimise the impact on traffic. Most roads affected will be fully or significantly resurfaced with a select few being only partially resurfaced or patched as required. There will also be some improvements to pedestrian facilities, traffic signal upgrades and renewal of some street furniture.

Listed below are the streets affected along with the proposed month/order of the works and traffic management. Please note this is subject to change following final confirmation from the contractor (MacLay Civil Engineering) next week. Neighbourhood notification letters will be issued to local residents and traders prior to the commencement of each phase.

Street

Month

Treatment

Proposed Traffic Mgmt

Abercromby Place

May

Fully Resurfaced

Road closure. Local diversion

North Leith Sands

May

Fully Resurfaced

Road closure. Local diversion

Albany Street

June

Fully Resurfaced

Road closure. Local diversion

Lindsay Road

June

Fully Resurfaced from North Leith Sands to Portland Street

One-way closure. Local diversion

Broughton Street

June

Full Resurfaced

Northbound Road Closure

Ocean Drive

June

Fully Resurface both northbound lanes from Lindsay Road to roundabout, and southbound bus stop at Holiday Inn

Road closure. Local diversion

East London Street

June

Fully resurface from roundabout to Cochran Terrace

Lane closures

Annandale Street

June

Fully resurface from Haddington Place to roundabout and from roundabout to Hopetoun Street

Road closure in 3 phases. Local diversion

Great Junction Street

June

Fully resurface from Cables Wynd to Henderson Street

Lane closures or Eastbound closure with local diversion

Dalmeny Street

July

Overlay setts in centre of carriageway (retain setts in parking areas)

Road closure. Local diversion

Hopetoun Street

July

Various sections resurfaced

full Road closure. Local diversion

Gordon Street

July

Fully resurfaced and overlay setts on Manderston Street

Road closure. Local diversion

McDonald Road

July

Resurface eastbound bus stop at Papermill Wynd

Lane closure or southbound closure with local diversion

Broughton Road

July

Fully resurfaced from Broughton Primary to Bonnington Road

Road closure in 2 phases. Local diversion

Links Place

July

Fully resurfaced

Road closure. Local diversion

Duncan Place

July

Fully resurfaced

Road closure. Local diversion

Bonnington Road

July

Fully resurfaced from Broughton Road to Corunna Place

Road closure in 3 phases. Local diversion

Academy Street

July

Overlay setts in running lanes (retain setts in parking areas)

Road closure. Local diversion

Newhaven Road

August

Fully resurfaced from Pilrig Street to Pitt Street

Road closure in 2 phases. Local diversion

East Hermitage / Restalrig Rd Junction

August

Fully resurface Junction area

Temporary Traffic Lights and closure of Links Gardens. Local Diversion

Duke Street / Easter Road Junction

August

Fully resurface roundabout and approaches

Temporary traffic lights

Pilrig Street

August

Fully resurfaced from Spey Street to Newhaven Road

Road closure in 2 phases. Local diversion

Easter Road

August

Various sections resurfaced

Various lane closures and temporary traffic lights. Possible road closure required at Albion Road with local diversion

Reporting noise nuisance from Seafield Waste Water Treatment Plant

A number of months ago we introduced one handy web from on our website which allowed members of our community to report nuisance & intrusive odours from Seafield Waste Water Treatment Plan to City of Edinburgh Council, Scottish Water, Veolia, Scottish Government and the Scottish Parliament.

As we have recently received a significant number of complaints relating to nuisance noise from the plant, we have updated our form, allowing you to report smell and / or noise from the plant.

The form can be accessed by clicking here, and can be used any time, any day.

 

 

Leith Links Community Council Meeting, 29 April, 6:30pm, Leith Community Centre

The next meeting of the Leith Links Community Council will be on Monday 29th April , at 6:30pm in the Leith Community Education Centre, New Kirkgate.

If you live in the area, you are warmly welcomed to attend.

Please find the Agenda for the next meeting here Agenda29.4.19

and minutes of our March meeting  Monday 25 March 2019

 

 

 

Leith Festival AGM & Board Member Recruitment

Leith Festival is an important annual event, only made possible by the massive support of our local community and volunteers willing to invest their time.

Their next AGM is due to be held on Wednesday 1 May 2019, at 7pm, in Leith Dockers Club.  Everyone is welcome to attend.  Click here to see their Facebook event.

They are currently seeking some new board members, including a Treasurer. So if you are looking for a new volunteering opportunity please do get in touch with them.

 

Click here to view Leith Festival contact details.

 

 

 

Leith Links Play Park

City of Edinburgh Parks Department confirmed yesterday that after discussion with the contractors work on the new Leith Links Play Park will start during w/c 21st April.

This is great news for the area as we come into summer .

The contractors haven’t confirmed how long work will take but I would hope that it will be in use by June? Watch this space for further updates.

Seafield Update

During 2017 the local community continued to suffer noxious smells and it was clear that the reporting system set up by Edinburgh City Council was ineffective. Difficult to use and response times poor.

In 2018 the CC introduced a reporting tool for the community to quickly report nuisance smells when it became clear that system set up by Edinburgh City Council (COEC) was ineffective, difficult to use and resulted in poor response times.

The link the CC set up is easy to use and we know that our locally elected politicians and public servants are aware of reports. More importantly the public servants we expect and trust with policing our complaints can’t ignore public concerns.

Between 09/07/18 and 19/08/18 there were 123 reports.

Then 09/09/18 to 23/11/18 19 reports.

During the most recent incident between 15/02/19 to 18/03/19 we received 57 reports

Scottish Water issued an update on 15/02/19 alerting the community to urgent work being carried out at Seafield due to build up of sludge. This was followed by an apology issued by Scottish Water on 26/02/19.

SEPA told the community they only received 1 complaint passed to them from COEC and they were not aware that there had been so many.

SEPA said to Leith Links Residents Association

Thanks for your email. I am sorry to hear the community have been experiencing odours. I have logged your email as an environmental event. The event reference number is ENV/0897328 and I can provide the update below.

SEPA did not receive any complaints about the site during the month of February 2019. We received one complaint on Friday 1 March 2019. Two officers attended the site on Friday 1 March and undertook an odour assessment on site and at two offsite locations.

Offsite the officers detected a faint whiff of sewage odour from the site. This was not deemed to be offensive. The odour detected offsite matched the odour detected on-site near the picket fence thickeners, which are unrelated to the activities covered by the Waste Management Licence and located outwith the Waste Management Licence boundary. Our findings were passed to City of Edinburgh Council Environmental Health on Monday 4 March.

The City of Edinburgh Council said

We can advise that we received a total of 83 Seafield odour complaints in February 2019, with 77 of these received between 24 and 28 February. Officers carried out 14 visits to the area, between 24 and 28 February, as a result of these complaints. In addition, four proactive assessments within the community were also carried out during the month and a plant inspection was carried out on 26 February.

We can confirm that mostly no or faint odours and occasionally moderate odours were witnessed on the visits made to the community during February 2019, which would not amount to what you refer to as a smell nuisance.

So although we received 57 complaint reports COEC didn’t think there was a problem. There is a problem for the local residents who have taken the time to report it.

I estimate that for every report made through the CC website there are probably 10 households who don’t

During February the CC has also been contacted by local residents because of noise which appears to have started about the same time that the most recent smell incidents were being reported. Veolia had to bring in mobile centrifuges to deal with sludge levels.

Leith Links CC received the response below from the City Council investigating noise

I refer to your emails below concerning a miscellaneous noise, causing disturbance over a wide area around Seafield / Restalrig. I’m sorry you had not received a reply, however we do not appear to have received your original email. We have now logged your complaint on our system.

With regard to the noise, I have two ongoing complaints in the
Seafield / Prospect Band area and received another from a resident in the Restalrig area yesterday. However, so far it has not been possible to witness the noise being complained off. Seafield Sewage Treatment Works (STW) were also contacted last year, however their investigations did not identify any unusual noise issues from machinery. A noise survey visit to one of the residents had been scheduled for last night, but was cancelled due to the high wind speed; as it affects noise measurements. The noise survey has been re-scheduled for next week.

Information provided from the original two residents who had complained and the fact that another two complaints have been received suggests that the noise is becoming louder and more persistent. Therefore it should make it easier to investigate the noise and determine the source.

I’ll give you an update once I have carried out the noise survey visit next week.

The noise stopped before any further investigation could take place about the same time the work stopped at Seafield.

On a balance of probability these problems are linked to Seafield.

The infrastrucure at Seafield is old and it’s failing on a more regular basis to cope with excessive levels of sludge. 

I also believe that during the most recent incidents there was a crisis at the plant that Veolia were trying to fire fight. Both SEPA and COEC have let the community down again by not investigating incidents properly.

We still have this mistaken belief by public officials that their noses and ears are better than those of the community.

Urgent action and investment at that the plant must be the way forward.

We haven’t even reached the normal smelly season during May.

Leith Links Community Council will continue to work together with the Residents Association and I promise to raise the communities concerns strongly at the next Seafield Stakeholders meeting scheduled for 260419

Jim

Public consultation on fireworks

A public consultation on the use and regulation of fireworks in Scotland is now live, running until Monday 13th May.

The Scottish Government seeks views on how people use and enjoy fireworks, the impact they have on people and communities across Scotland, as well as their impact on animals. It also seeks views on the sale of fireworks to the general public, and ideas on what action can be taken to ensure fireworks continue to be enjoyed safely and responsibly.

While much of the current legislation on the sale of fireworks is reserved to Westminster the consultation will help to identify gaps, issues or unintended consequences with the current regulatory framework.

Alongside the consultation, there will be a series of engagement events to create opportunities for members of the public, alongside local partners, to deliberate on the key issues and discuss with others what could be done going forward. Details of events alongside access to the consultation on Citizen Space can be found via the following link https://consult.gov.scot/safer-communities/fireworks/

The consultation events that have been organised so far:

  1. Wednesday 13thFebruary, 6- 8 pm at Craigroyston Community High School, Edinburgh
  2. Monday 18thFebruary, 5 – 7 pm at Pollokshields Community Centre, Glasgow
  3. Thursday 28thFebruary, 1-3 pm and 5-7 pm at The Attic, Tolbooth, Stirling
  4. Tuesday 5thMarch, 2-4 pm at New Register House, Edinburgh
  5. Tuesday 19thMarch, 2-4 pm and 6-8 pm at Perth Leisure Pool, Perth
  6. Thursday 21stMarch, 2-4 pm at Spectrum Community Centre, Inverness
  7. Thursday 21stMarch, 6-8 pm at Jurys Inn, Inverness
  8. Monday 29thApril, 2-4 pm and 6-8 pm at Civic Rooms, Town Hall, Aberdeen

Events are also being planned in Elgin, Paisley, Dumfries and Galloway and the Islands.

Leith Links Community Council meeting Monday 25th February

The next meeting of Leith Links Community Council will be on Monday, 25th February, in Leith Community Centre (Shore Room). Please remember the new start time is 6.30pm.

If you live in the Leith Links area, and have questions or concerns to discuss, we would be pleased to welcome you.

Please find Agenda and draft minutes of last meeting attached.

agenda  Agenda25.2.19 minutes Draft2LLCC Minutes Jan 2019

 

Leith Links Community Council meeting Monday 28th January

Happy New Year from LLCC

The next meeting of Leith Links Community Council will be on Monday, 28th January, in Leith Community Centre (Shore Room). Please remember the new start time is 6.30pm.

If you live in the Leith Links area, and have questions or concerns to discuss, we would be pleased to welcome you.

Please find Agenda and draft minutes of last meeting attached.

DraftAgenda 28.1.19,, LLCC Minutes Draft Nov 2018Jan21st-converted (1)

 

 