Works Start Date (Pilrig Street to Crown Place)

Following discussions with our contractors, Crummock (Scotland) Ltd, the mobilisation timescales forthe next section of the Leith Programme have now been confirmed in more detail.

 Crummock staff will have a site presence in the area from 12 May in order to carry out a dilapidation survey of sections 5-8 (Pilrig Street to Crown Place)A ‘dilapidation’ survey records the condition of properties around the worksite prior to works commencing.

The construction work is scheduled to commence in the week beginning 19 May. This information supersedes that provided in the earlier stakeholder update of 9 April.   

 General questions regarding the work can be addressed to the City Centre and Leith Neighbourhood Team, citycentreteam@edinburgh.gov.uk, or 0131 529 7061. Issues related to the works on site, such as access enquiries or concerns can be directed to myself, in the first instance, as I will be based in the area and available on mobile number 07739 188438 or email alan.dean@edinburgh.gov.uk