Leith Programme Update The Foot of the Walk junction works

The contractors carrying out the upgrade works to the Foot of the Walk junction (MacLay Civil Engineering Ltd) are anticipated to start mobilising next week, commencing 9 February, with full presence on site expected week commencing 16 February.

 The works, aimed at simplifying and improving the crossing for pedestrians, are expected to take 15 weeks to complete. In addition to road and footway resurfacing, the redesigned junction will see 4 single stage pedestrian crossings installed at the bottom of Leith Walk, Duke Street, Great Junction Street and Constitution Street. Once fully operational the junction crossing will include an all pedestrian phase allowing those on foot to cross more easily than at present improving the overall accessibility of the area in line with the design principles of the Leith Programme.

 For the duration of these works, Constitution Street will be closed at its junction with Leith Walk as part of the traffic management arrangements in place aimed at minimising disruption to traffic flow as much as possible. Local access to this area will be via Laurie Street, Queen Charlotte Street, or Bernard Street. Three way temporary traffic lights will be in operation at the main Leith Walk junction to control traffic flow. It is anticipated that traffic management arrangements will commence on 16 February.

 Bus diversion and general traffic conditions information reminder:

Details of the most up to date information regarding any bus diversions and traffic conditions affecting Leith Walk please visit either of the sites below:

https://twitter.com/on_lothianbuses

 https://twitter.com/edintravel

Ongoing Works – Pilrig Street to Crown Place:

Crummock (Scotland) Ltd, contractors on the Pilrig Street to Crown Place section, are continuing with localised remedials and the completion of outstanding works including bus tracker connections and the installation of cycle racks, road markings and associated signage. Getting the latter fully installed is important as this will allow the enforcement of the new parking regulations to commence. Details of these new regulations will follow in a separate update.

 New Design Layout:

The new design of Leith Walk, north of Pilrig Street, with additional formal and informal pedestrian crossing points appears to be working well at this early stage with pedestrians, cyclists and drivers getting used to the new pedestrian friendly layout and crossing locations. One of the main aims of the Leith Programme is to make the area more accessible and safe for those on foot and we would ask that all road users become familiar with the new layout and respect all the pedestrian crossing points.

LEITH DECIDES 2015 SATURDAY, 7TH FEBRUARY

£eith decides is a Leith Neighbourhood Parnership initiative. It is a method which gives over the decision making power on the allocation of community grants to the people of Leith.You can find out more here: http://www.edinburghnp.org.uk/neighbourhood-partnerships/leith/about/%C2%A3eith-decides/There are 37 local projects from which to choose this year.  Leithers are asked to cast their vote on how to allocate £22,092 in grants of up to £1,000.
Sat 07 Feb 2015 – 12:30 pm – 3:00 pm
Leith Community Centre
Kirkgate, Leith
Edinburgh

Safe Leith Action Group, Meeting on 24th February

Following the creation of the Leith Local Community Plan for 2014 – 2017, the above action group has been established to deliver two of the Leith local plan priorities;

·         Develop closer links between the community and safety services

·         Raise awareness of how to report safety concerns

Our first task is to get the community, community representatives etc together to create an action plan, to be coordinated by the Safe Leith Action Group, to plan how the community & organisations can work together to address the above two priorities.

 I would like to everyone who lives, works, studies, volunteers or visits Leith to attend our public meeting on Tuesday 24th February, from 6pm in McDonald Road Library, those who cannot attend can still have some input into the meeting by completing our brief survey, the responses gained will be fed into the public meeting.  The survey can be found athttps://www.surveymonkey.com/s/B6MHCC8.

 Members of the community can attend the meeting and / or complete the survey as well.

 The more people who feed into the action plan, the better!

 Kind Regards

 Michael

Michael Traill | Community Safety Officer | City Centre / Leith Neighbourhood Office | Services for Communities | The City of Edinburgh Council | Room 9.01, 329 High Street, EH1 1YJ | Tel 0131 529 7061 |  

Leith Links CC Next meeting, Monday, 26th January 7pm

Happy New Year from Leith Links Community Council. The first meeting of 2015 takes place on Monday, 26th January in Leith Community Centre, New Kirkgate at 7pm prompt. If you live in the area covered by LLCC and have an interest in making your community stronger we would happy to see you. Agenda and minutes of last meeting will be issued prior to the next meeting.

Happy New Year from LLCC

On behalf of Leith Links Community Council may I wish everyone a very happy, peaceful and hopefully fruitful New Year. If you’ve made your resolutions please consider adding another. If you have a surplus of canned food which was bought for guests and never used then consider donating them to the Edinburgh North East Foodbank based in Henderson Street. There’s also one which covers North West depending on where you live. It’s unfortunate that there is a need for an increasing number of foodbanks in all parts of Scotland. If you can give a little help please have a look at the links below.

www.edinburghne.foodbank.org.uk

www.edinburghnw.foodbank.org.uk

Leith Programme Update

Leith Programme Stakeholder Update 64

 Progress Update:

 Although some time has been lost due to the recent weather conditions, Crummock (Scotland) Ltd are still anticipating that the main contracted works will be completed by 19 December with any remedial works being carried out after the New Year. It should be noted that the completion of certain parts of the remaining contracted works are weather dependent such as the installation of road markings and anti-skid treatments. The contractors will continue to monitor the weather forecasts and endeavour to get everything completed as planned.

 Summary of Progress

 Section 6b West (Balfour Street junction northwards)

·         Minor pointing and road sign installation to complete

 Section 6b East (Lorne Street junction southwards)

·         Pointing and road sign installation to complete

 Section 8b West (Jane Street to Casselbank Street)

·         Minor pointing and road signs installation to complete

Section 8b East (Manderston Street to Crown Street)

·         Minor pointing and road sign installation to complete

 Section 8c West (Casselbank Street area)

·         Minor pointing and road sign installation to complete

Section 8c East (Crown Street northwards):

·         Minor pointing and road sign installation to complete

 Carriageway

·         Raised tables at junctions complete with exception of Jameson Place, Smith’s Place and entry to current site compound

 Weekend Working – 13 December

The contractors will be carrying out footway works on Saturday 13 December 2014.

Looking ahead for next week:

·         Continue with footway inspections and remedial works

·         Container bin recess north of Pilrig Street junction

·         Concrete under slabs at area north of Iona Street junction

·         Asphalt works at Arthur/Balfour Street

·         Complete raised tables at Jameson Place, Smith’s Place and entrance to current site compound

·         Testing and commissioning of lights and crossings

·         Installation of poles and road signage

·         Complete road line markings and anti-skid treatment

 Bus diversion or traffic delay information reminder:

 For the most up to date information regarding any bus diversions and any traffic delays affecting Leith Walk please visit either of the sites below:

 https://twitter.com/on_lothianbuses

https://twitter.com/edintravel

 

DUNCAN PLACE RESOURCE CENTRE

I was saddened to read the article in the Evening News’Neglected centre to be razed over repair bills’ but wasn’t surprised. When I first became involved with Leith Links CC our meetings were held in a church hall but we moved to Duncan Place to show our support for this community asset. I’m happy to be corrected but prior to the last City Council elections possibly 4 or 5 years ago I attended a meeting and the same repair cost figure of £3.5 million was quoted but nothing was done.(Strange how the figure hasn’t increased) The£387,000 for the lift which would have made the centre accessible for the disabled was allocated and ring fenced by the city council well before my time on the CC but nothing was done. The money has layen untouched over the years with someone wondering how they could get their hands on it to be used in the budget black pit. According to the News this money will now have to be pay for the building being pulled down. You couldn’t make it up but this appears to be another symptom of council mismanagement which when added to other failures has resulted in the population of this fine city facing cuts to chip away at the massive debt faced by the council. The building has always been well used by the local community but I fear that the real decision on its future was made many years ago by council officials and not elected councillors that it would be closed. The lack of necessary repairs which were identified in 2008/9 have allowed the building to deteriorate to the point where the only option appears to be to demolish it. Will any council officials be taken to task, reprimanded or dimissed? I’ll let you answer that one.

Edinburgh’s budget challenge

Budget Question Time

 7.00–8.00pm, Monday 1 December 2014

City Chambers, High Street, Edinburgh

 As a representative of your community or interest group, we would like to invite you to be part of our Budget Question Time event. This event is to give members of the public the opportunity to quiz our panel of senior councillors on the Council’s budget proposals for next year and beyond.

 The proceedings will be chaired by Edinburgh Evening News Editor, Frank O’Donnell, and broadcast live via the Council website.

 If you would like to put a question to the panel, or just come along and be part of the audience, please complete this short online questionnaire by Monday 24 November. Please note that places are limited. If you are not able to attend please pass the invitation on to another representative.

This is a great opportunity to play your part in Edinburgh’s budget challenge but you can also get involved before 19 December 2014 by:

 ·        watching our short animated film

·        take the budget challenge with the online budget planner

·        taking a look at the 2015/16 budget proposals overview, or   download the full proposals.

Person completing online budget planner

Your feedback will help the Council to make its final budget decisions on 12 February 2015.

Find out more

www.edinburgh.gov.uk/budget

1 14 15 16 17 18 34