Community Councils Together on Trams: Note of meeting held on 25 April 2019

Leith Links Community Council is a member of ‘Community Councils Together on Trams’ alongside Leith Central Community CouncilLeith Harbour & Newhaven Community Council and New Town & Broughton Community Council. CCTT is the coalition of Community Councils who meet regularly to discuss, scrutinise and influence the intended continuation of the Edinburgh Tram system to Newhaven.


1. Welcome, introductions, minutes

2. Update TT team

a. Progress on CEC work on multi-year environmental cost/benefits post-tram

  • Noted: this is being progressed by Hannah Ross (HR) who will advise

b. Confirmation of official ECI period (given the delayed mobilisation)

Noted: ECI is underway, but not all senior contractor staff are in Edinburgh. ECI will end 9 October 2019. Lane closures with heras and barrier will commence from 10 October 2019. To confirm the track slab design the contractor will carry out ground and site investigation along the route[note i]. This will be carried out via trail holes and bores. These works will be carried out under minor traffic management lasting on average 5 days per location.

  • Noted: DW as ‘in-house’ stakeholder rep, and contractors are co-locating to 200 Bonnington Rd (200BR) for the period (perhaps beyond); other members of TT: HR (ca 1 day at 200BR) and RL (as required at 200BR) based at their respective main offices. New TT communication person is being recruited. Client team includes CEC tram team, Anturas, Turner Townsend, Atkins.
  • Agreed: DW to provide diagram of all entities and key personnel involved and glossary of acronyms
  • Noted: detailed trader logistics survey in progress; more info at next meeting

3. Update CCTT

  • Noted: HT had meetings with Paul Lawrence, Hannah Ross and George Lowder to prepare the ground for CCTT/TT meetings during ECI period
  • Noted: the role of the Traffic Management Review Panel (TMRP): includes representation of some but not all relevant groups (e.g. pedestrians and bus passengers – as opposed to bus operator – don’t have a dedicated voice)[note ii]
  • Agree ‘shopping list’ (see below) priority, scope, input required, date decision required
  • Agreed: see bold items in table below

4. Agree future meeting dates during ECI period

  • Agreed: monthly meetings at 200BR on last THU, apart May (date tbc) and July (holiday[note iii]): 29 (tbc) May, 27 June, 29 August, 26 September; meetings beyond September TBA
  • Agreed: due to pace of mobilisation, to meet contractors’ senior staff at June meeting
  • Agreed: to keep an eye on Constitution Street fixing points and pre-works
Priority Topic (subtopic) Scope Input required from Date decision required
TTROs in wider corridor (i.e. including diversion routes and their side streets) There will be a blanket road works embargo.
May meeting business logistics[note iv] TT will share analysis of survey.
bus diversions/stops: this will need LB input The role of TMRP was noted.
Detailed design:
May Meeting: DW to provide info on tracker timing Bus stops/shelters (this will need LB and maybe JCD input) Any bespoke shelters to be provided by JCD; integration with new tracker system (if any) to be confirmed.
June meeting with Gareth Barwell Communal bin locations along the route: may require some infrastructure (example: Albert Street) and changed waste collections procedures (regularity, times outwith tram operation hours) ‘95% complete’
‘open’ (CCTT definition) design items at Shrub Pl, Constitution Street (we discussed best approach) and Ocean Terminal bus logistics and access to private road ‘Shrub Place design issues are a locality issue and are not being dealt with by the project’; Ocean Terminal issue has been resolved
construction period: monitoring/quality control, reporting, communications To be discussed in more detail in future
Utilities: embargo on non-emergency work in wider area (?); clear deadline to complete other work during ECI There is a blanket embargo on such works.

[i] HT note: I seem to recall that exploratory digs would occupy only one lane and last 48 hrs max

[ii] DW note: Major roadworks across the city are coordinated and managed via the City Wide Traffic Management Group (CWTMG); to assist with this process a dedicated Trams to Newhaven Traffic Management Review Panel (TMRP) has been established. Membership of this group is similar to the CWTMG including Emergency Services, Transport Operators and Council Officers. Although not on the approving body, traffic management will be discussed with the Active Travel Forum which has membership from Living Streets, Spokes, Edinburgh Access Panel, Transform Scotland and Sustrans.

[iii] HT note: this leaves only four meetings to address a hefty ‘shopping list’

[iv] While operators contacted by SLTN were all positive about the project, they expressed concern about disruption to deliveries as well as a general drop in footfall for the duration of the works. Communication from the council was said to be key.
Garry Clark, development manager for Edinburgh at the Federation of Small Businesses, said: “Local businesses need to be able to plan in order to mitigate the impacts that the tram extension will have upon their businesses. “Whilst the council has gone out to businesses early this time around, firms are telling us that they need clarity on the timescale of the work to enable them to put these plans in place. (https://sltn.co.uk/2019/04/18/council-must-be-vocal-on-trams)

Community Councils Together on Trams: Minutes of meeting held on Thursday 21 February 2019

Leith Links Community Council is a member of ‘Community Councils Together on Trams’ alongside Leith Central Community CouncilLeith Harbour & Newhaven Community Council and New Town & Broughton Community Council. CCTT is the coalition of Community Councils who meet regularly to discuss, scrutinise and influence the intended continuation of the Edinburgh Tram system to Newhaven.

 

Abbreviations

BAFO = best and final offer LLCC = Leith Links Community Council
CCTT = Community Councils Together on Trams LW = Leith Walk
CEC = City of Edinburgh Council NTBCC = New Town & Broughton Community Council
CPZ = controlled parking zone OBC = outline business case
CS = Constitution St POLHA = Port of Leith Housing Association
ECI = early contractor involvement SPC = swept-path contract
EIA = environmental impact assessment TAPOG = CEC’s tram all-party oversight group
FBC = full business case TfE = Transport for Edinburgh
ISC = infrastructure and systems contract TN = Trams to Newhaven project
LCCC = Leith Central Community Council TRO = traffic regulation order
LHNCC = Leith Harbour & Newhaven Community Council TT = trams team

TAPOG is CEC’s leader and vice-leader, CEC’s transport convenor and vice-convenor, and transport spokespersons from each party

1 Welcome, introductions

1.a Attendance

Charlotte Encombe CCTT/LCCC Rob Levick CCTT/LHNCC Harald Tobermann CCTT/LCCC
Angus Hardie CCTT/LL CC Jennifer Marlborough CCTT/LHNCC Bruce Ryan CCTT minutes secretary
Allan Jack CCTTNTBCC Andrew Mackenzie CCTT/LLCC Darren Wraight TT/CEC
Rob Leech TT/TN project Carol Nimmo CCTT/NTBCC

1.b Apologies

None

2 Update from TT

Rob Leech outlined the next steps for the final business case (FBC), and the main points of its contents.

2.a Next steps

The FBC is on (post-BAFO) schedule. It goes to

  • CEC’s transport and environment committee on 29 February
  • CEC’s finance and resources TEC committee on 7 March, to consider procurement and contracts
  • Full council on 14 March.

2.b Contents

Minuter’s note: subjunctive (‘would’, ‘should’) is used where relevant because many things will only happen if CEC approves the FBC.

2.b.1 Background

  • This project is about completion of phase 1a of the original tram scheme.
    • This should have been completed years ago, i.e. along with the existing line from the airport to York Place.
  • The existing line is performing ‘extremely well’, e.g. 7m passengers in 2018.

2.b.2 Contents

  • The FBC has been updated (from the outline business case [OBC]) to take account of tendered prices, inflation, design-changes (resulting from consultations) and the ‘support for business’ package.
  • The FBC has a section on lessons learned from building the existing line. This includes information on retaining knowledge from that project .
  • It has been prepared in accordance with Scottish Government and UK Government guidelines.
  • It contains much on the strategic case, i.e. reasons for building this extension.
    • Edinburgh’s population is set to grow by 20% by 2039.
    • Employment will also grow by 7% by 2022.
    • There is low car-ownership in the Leith area and the Leith Walk corridor.
    • CEC wishes less car-ownership/more sustainable transport, i.e. shift from private motor vehicles to public transport.
    • There is very high population on the corridor where this extension would run.
    • There is content on connectivity between employment centres, and employment during and after construction.
    • There is content on sustainable development at the waterfront.
      • Good public transport enables reduced car-dependency in such areas, hence enabling different life-choices.
      • That is, it allows people to live near their work; it reduces need for commuting and urban sprawl.
      • This would lead to improved air-quality in the tram corridor.
    • The extension would enhance Leith and Newhaven as destinations.
    • Hence chapter 3 (the strategic case) covers how this project would
      • follow UK treasury guidance (the ‘green book’), and CEC policies and strategies, e.g. local development plan
      • link 3 out of four economic centres in Edinburgh: airport/international business gateway/Edinburgh park; city centre; Leith waterfront. (Tram would not serve the SE quarter economic centre.)
    • Overall, the FBC presents tram as an enabler for growth that would not occur without it.
  • Concerning the economic case:
    • The capital cost is set to be £196m. (It was £165m in the OBC.)
      • This allows for risk, using a quantitative analysis using ‘green book’ methods.
      • It includes an amount for contractor-pricing. This was initiated by the collapse of Carillion, leading to contractors undertaking much more due diligence when tendering.
      • It also includes inflation and design-changes.
      • It also includes the ‘support for business’ package.
      • There will also be two contracts, hence increased contract-management overheads. (Management will be by a blended team, including a delivery unit containing experienced light-rail consultants, and senior CEC officials such as D Wraight. At peak, there will be around 30 CEC managers in this project.)
      • Early contractor involvement (ECI) adds some management overheads, and adds 6 months to the programme.
    • In addition to the £196m, £10m has been added for optimism bias (OB), following government guidance.
      • This takes the total cost to £207·3m, giving a benefit to cost ratio of 1·4:1. (In public transport schemes, this ration is expected to be between 1·2: 1 and 2:1, because public transport has quite high construction and operational/maintenance costs. The OBC had 1·64, but the majority of the change here is due to changed government guidance on costing time.)
      • At the start of a process (before design starts), the ‘green book’ mandates a large OB (66%). However, there is then a sliding scale based on Network Rail’s GRIP design process. This scale moves from optimism bias to quantitative risk analysis (QRA). SO FBCs should be base costs + an amount from QRA. (Economic cases should include OB, but the guidelines are ambiguous about inclusion of OB in financial cases. TT has assumed 6% OB. The OBC had 20% OB in its economic case, but not in its financial case.)
      • Also, professor Bent Flyvbjerg and colleagues have an alternative method for calculating risk, based on an ‘outsider’ view using information from similar projects about projected and actual costs. (The UK and Scottish Governments do not currently accept this method.) Flyvbjerg and colleagues calculated this project’s capital cost as £257m, not £207m. However, they recognise that the project is very advanced from the initial design stage, that some utilities have already been moved, and that this project is an extension of an existing line, not de novo. These could reduce the overall cost but such reductions are not part of their model.
      • Hence £50m (£257m – £207m) has been earmarked as a contingency to be managed by CEC’s head of finance and a finance and risk subcommittee (reporting to the project board).
      • The impact of such drawdown would increase the 2024-27 borrowing from £1·9m to £14·8m. This level of borrowing would be repaid by 2037.
      • The FBC hence considers mitigation, e.g. borrowing at less than 4·1%, moving away from parity of fares between bus and tram, and optimising tram maintenance and infrastructure costs.
    • The economic case is also based on patronage forecasts of 15·7m in 2023 (first year of operation).
      • This comes from high population densities and increased development on the corridor, e.g. Cala development.
      • Increased patronage would come from bus and car, i.e. people would use trams rather than buses.
      • Suitable wording in the FBC has been agreed with Lothian Buses (LB), recognising that this project is part of an integrated public transport framework. This section also covers what LB needs to remain robust during and after construction. These include clear radial routes into the city, e.g. double-red lines at the Roseburn shops. Hence LB wants CEC to enforce route-clarity more strongly than is done today.
      • (C Encombe suggested that implementation of a CPZ in LCCC’s area would help enhance route-clarity.)
      • (H Tobermann suggested that historically CEC has not enforced well in the past, and questioned why LB has not asked for route-clarity enforcement previously.)
    • This extension was always the part that would make Edinburgh trams financially positive.
    • There are also anticipated wider benefits, which may add between 15 and 40% to the economic case. (There is no agreed method for assessing their financial value, so they have not been monetised in the FBC.)
      • These benefits include employment opportunities, connectivity (agglomeration of businesses), linking brownfield sites with other economic centres to provide more opportunities, higher population densities.
  • The financial case centres on future tram revenues, but also relies on £20m dividend over 11 years from Lothian buses.
    • LB already pays a dividend to CEC.
    • In early years during construction, there is drawdown of money, but no revenue [from ticket sales].
    • There would be a cashflow-issue (2024 to 2027) of £1·9m. This would come from CEC’s reserves. Later, revenues should grow, enabling replenishment of CEC’s reserves.
    • This use of reserves would cause an opportunity cost. (Examination of this was inspired by the Hardie enquiry.)
    • The extension would give Edinburgh £395m economic benefit (net present value) over 60 years.
      • The FBC includes downward sensitivity-testing, around patronage and cost of borrowing. This assumes 4·1% interest, but CEC can borrow more cheaply than that. It also assumes no loss of revenue from stoppage.
  • The FBC also includes a commercial case.
    • This covers ECI and contract-conclusion.
  • The FBC also includes a management case.
    • This covers how the project will be implemented, e.g. heritage and archaeology work, large work-sites, no double-digging, support for businesses, governance.
    • There is also a section on supplementary projects. It has been agreed that CEC would fund these (e.g. from its active travel and capital roads budgets) in parallel with the tram-work. However, these are outwith the tram-project’s limit of deviation and are hence not part of the FBC. It is very likely that TT will deliver these supplementary projects.
      • The supplementary projects do not include integrated ticketing.

2.b.3 Q&A

Minuter’s note: the information in some answers has been included at relevant points in the above, so is not repeated here.

  • The cost of the completion phase is ¼ of the cost of the initial phase because the initial phase is ‘extraordinarily expensive’. Building from lessons learnt from the original tram project, firstly the contracts for this project use NEC industry standards. (The contracts for the original project were bespoke.) This form of contract mandates that contractors cannot stop work if there are (contractual) issues, and that contractors will continue to be paid.
    • Secondly there are large work sites, so contractors can (and are contractually required to) continue work in other, non-problematic areas while problems are being resolved.
    • Thirdly, excavations for utility-diversions would not be covered over, and then re-dug to enable construction. Instead, a swept-path process would be used: excavations would be dug, utilities diverted, then construction would occur. Because there would be several stretches of work using this method, if a problem occurs in any area, work can continue in other (parts of) stretches while problems are being resolved.
  • The contracts now use the NEC4 standard, rather than NEC3. The main difference is that NEC4 mandates a project bank account from which main subcontractors are paid directly. Hence, should the main contractor become insolvent, the main subcontractors would continue to be paid. This would also enable ECI.
  • There are two incentive mechanisms in the contracts:
    • During ECI, there is an incentive mechanism to reduce costs: this would benefit both the contractors and CEC.
    • Once construction starts, a ‘pain-gain’ mechanism would start on the Infrastructure & Systems Contract. That is, should costs exceed the target price, CEC would share the costs 50/50 with the contractor up to a threshold of 120% of the target price, thereafter the risk is with the contractor for all the main civil engineering works. Should costs be less than the target price, CEC and the contractor would receive equal shares of such savings. Hence th contractor would have a ‘massive’ incentive to deliver for less than the target price.
    • However, there is no incentive to cut corners. While the contractors are self-certifying. CEC’s technical services (provided by Atkins) will check contractors’ designs as they arrive. Similarly, TT will employ 3 quality-control inspectors (1 during ECI). Their sole responsibility is to be on site all through the work, checking that everything is as per the designs. TT will also inspect the inspections.
  • Price-increases were partly cause by market price-testing. (R Leech is not privy to the actual contractors’ costs for each part of the design.) However, it is very likely that risk has been priced into the costs. There were risk-costs in the OBC’s £165m costs.
    • H Tobermann stated that the construction cost has increased more from the OBC cost than he would expect.
    • R Leech responded that probably as a result of Carillion’s collapse, contractors took a more diligent approach to tendering. RL believes this is a positive step because it means prices are realistic, and contractors really understand what they are taking on. (Too often, they haven’t known, so ‘disasters’ happen during work.) ECI also adds to this positive effect.
  • TT has closely followed the evidence presented to the Hardie enquiry. It has also undertaken its own ‘lessons learnt’ process, based on knowledge from people who were involved in the original work.
    • It was suggested that the people available to this process were only involved in ‘rescuing’ the original project, so they know what went wrong but not what caused this. However, RL stated that people with knowledge of the original project, pre-mediation, are available to advise the project. Physical work would start before the end of 2019. However, ECI work will start before this, leading to some minor road-works and accompanying traffic-management. An outline of the main works is on the TT website.
  • The principles for landscaping designs have been created but detailed designs for areas such as Elm Row have yet to be finalised. This will specify details of trees etc.
  • It needs to be decided whether and how these CCTT/TT meetings will continue. However, RL believes that they have been beneficial. D Wraight stated that other groups have asked how they can be involved in these meetings.
    • H Tobermann suggested that further meetings should cover the timetable and [CCTT’s list of] supplementary projects.
  • Much documentation is being published along with the FBC. Stakeholders will be emailed when the FBC and accompanying documents are published, giving links to them.

Community Councils Together on Trams: Minutes of meeting held on Thursday 30 January 2019

Leith Links Community Council is a member of ‘Community Councils Together on Trams’ alongside Leith Central Community CouncilLeith Harbour & Newhaven Community Council and New Town & Broughton Community Council. CCTT is the coalition of Community Councils who meet regularly to discuss, scrutinise and influence the intended continuation of the Edinburgh Tram system to Newhaven.


Abbreviations

BAFO = best and final offer LW = Leith Walk
CCTT = Community Councils Together on Trams NTBCC = New Town & Broughton Community Council
CEC = City of Edinburgh Council OBC = outline business case
CPZ = controlled parking zone POLHA = Port of Leith Housing Association
CS = Constitution St SPC = swept-path contract
ECI = early contractor involvement TAPOG = CEC’s tram all-party oversight group
EIA = environmental impact assessment TfE = Transport for Edinburgh
FBC = full business case TMRP = Traffic Management Review Panel
ISC = infrastructure and systems contract TN = Trams to Newhaven project
LCCC = Leith Central Community Council TRO = traffic regulation order
LHNCC = Leith Harbour & Newhaven Community Council TT = trams team
LLCC = Leith Links Community Council

TAPOG is CEC’s leader and vice-leader, CEC’s transport convenor and vice-convenor, and transport spokespersons from each party

1 Welcome, introductions

Attendance Apologies
Charlotte Encombe CCTT/LCCC Jennifer Marlborough CCTT/LHNCC Harald Tobermann CCTT/LCCC
Rob Leech TT/TN project Andrew Mackenzie CCTT/LL CC
Rob Levick CCTT/LHNCC Bruce Ryan CCTT minutes secretary
Angus Hardie CCTT/LL CC Darren Wraight TT/CEC

2 Update from TT

2.a Summary of current status

D Wraight noted

  • TT is still on target for its programme, so no amendments are needed to a programme document circulated by HT.
  • TT is building up to Transport & Environment Committee meeting on 28 Feb, and to full Council on 14 March .
  • They still need to complete political briefings, and open a data room for CEC members to scrutinise the business case.

Action CE to forward most recent programme document to BMR.

2.b Supplementary projects

2.b.1 Foot of the Walk to Ocean Terminal options appraisal around active travel

  • Stakeholders convened before Christmas
    • These include active travel groups, POLHA, local elected members and C Encombe as CCTT representative
    • The objective of this meeting was to set key objectives for the appraisal. One of these is affordability criteria.
    • Action: D Wraight to supply agreed key objectivesinfo [AECOM’s slides) to BMR and other CCTT members
      • NB this is not for publication, simply because it is not TT/DW’s document, but the information can be used.
  • Stakeholders reconvened on 14 January with AECOM to consider strategic corridors in this area.
    • Initial suggestions were derived by AECOM from the local development plan, active travel plans, key locations, trip generators etc. Then a workshop considered whether AECOM’s suggestions were correct. (They were.)
    • The strategic corridors are Constitution St, Newkirkgate to Kirkgate, Henderson St, Great Junction St, and east-west routes (Salamander St, Ocean Drive)
    • Then local links into these strategic corridors were considered. Many such links are already on the active travel plan.
    • Debate focussed on Leith Links’ connections with the corridors.
    • POLHA’s input about their properties was useful in this discussion, e.g. to consider use of Links Lane by children
  • Now AECOM will collate information and score each corridor and link against the key objectives.
  • They will report within 6 weeks of 14 January.
  • Then there will be a further discussion, then a public consultation. The format of the consultation depends on the outcomes of preceding steps.
  • AECOM will also provide high-level figures (presumably costs) for the full council meeting in March.
  • However, the other steps, including the consultation, will not be complete until May 2019. At this point, there will be a fully costed and consulted design for this region. It will then be CEC’s decision whether to proceed with construction.
  • This appraisal process has been funded by Sustrans.
  • CEC has not yet funded any construction that might stem from this appraisal process.
    • Sustrans has offered 50% match-funding.
    • Other funding arrangements are also being discussed with Sustrans.

It was noted that C Encombe and/or A Hardie may be CCTT’s representative in relevant fora, and that AECOM might also present to CCTT. There was then a discussion of where is and isn’t cycle-friendly in the area.

2.b.2 Duke St roundabout (bottom of Easter Road)

D Wraight noted that the current roundabout needs to be removed during tram-construction because of extra traffic that will then be using Easter Road. Temporary signals would allow traffic to enter the junction sooner, reducing congestion. Also, CEC transport staff wish to replace the roundabout with a signalised junction to deal with current congestion, but don’t currently have budget to do so. The junction is also considered not to support pedestrians or cyclists.

The predesign is complete, and detailed designs are in progress. Building is due to be completed in summer 2019. It was noted that if there is a TRO, there will be relevant consultation. Active travel aspects will also require some consultation. So DW expects that at minimum, community councils will be consulted

2.b.3 Duncan Place

There are three questions about [work on] this area: (1) Can it be extended to include Academy St and Wellington Place? (2) Can the road condition be improved? (3) What is the final look of these streets to be?

Predesign is in progress, following consultation, by the capital roads team DW anticipates CRT will opt for a renewal (i.e. resurfacing, possibly also look and feel, including maybe reconsideration of one-way systems) of these streets around summer 2019. AECOM is also looking at active travel in this area. This study may also affect the renewal/look and feel work.

2.b.4 Controlled parking zones and other items not [necessarily] on TT’s list

  • C Encombe noted that a Leith CPZ is third priority on CEC’s list of potential CPZs. (Corstorphine 1st, Morningside 2nd.)
    • DW noted that he, A Mackenzie and J Marlborough attended a meeting with local councillors about CS, where CPZs were discussed. Cllr Booth has contacted a relevant CEC official, and received a response, so this topic is ‘open’. DW also noted that despite the priorities, when major projects come online, relevant other/additional features must be considered. Hence the Leith CPZ is ‘open to discussion’. C Encombe noted the community strength about Stead’s Place, and suggested that this strength may influence CPZ decisions. (A Mackenzie noted that CPZ discussion was mostly about Leith Central’s area.)
  • Action: DW to ask Cllr Booth to share with CCTT the reply he received about the CPZ priorities.
  • C Encombe noted that Monty Roy has not received a response about issues affecting her police box. (DW noted that he has received MR’s communication.) Shrub hill work is encroaching onto the pavement, hence affecting MR’s business.
    • DW noted that TT has liaised with all developers along the tram route, and so knows what will impact the tram designs. MR’s issue should be handled by the locality team. DW also noted that despite police boxes are not deemed as fixed buildings, this one is now on TT’s drawings, and that DW would contact MR in the immediate future.
  • J Marlborough noted a new application to build a car-park on Ocean Drive to serve MV Fingal and Port Authority staff The relevant drawing implies the car-park would encroach on the tram route. Action: DW to investigate this potential issue
  • Constitution St
    • DW noted that he met with relevant CEC cllrs, Am and JM about this area. Prior to Xmas, DW was tasked with investigating parking and loading arrangements.
      • It was felt that creating such facilities in the church area was disrespectful and impractical, so the soft landscape area at Kirkgate House (KH) was considered for both parking and some loading facilities.
      • This week, TT’s recommendations around two design options will be taken to TAPOG. In general, option B is likely to be taken forward, with the caveat that other thing must be provided. Option B involves centralised tram-tracks, widening the footpath either side, introduction of a general traffic restriction at some point between Coatfield Lane and Laurie St (hence no parking or loading in this section). It also involves reinforcement of the pavement on the east side of CS to allow use of scaffolding and relevant vehicles directly outside houses. Option A had been rejected by the CS meeting.
      • The time-frame for restrictions is as yet undecided, but some local councillors prefer 7am to 7pm. Such restrictions on traffic are desirable because at peak hours there is much pedestrian use of relevant streets.
      • At TPOG, it was decided that this is part of the TRO considerations, and more work is needed to decide timing.
      • In the soft landscape area adjacent to KH, TT proposes providing loading facilities for up to 3 vehicles.
      • TAPOG has signed off moving forward with option B with loading provision and path-reinforcement before other tram-work starts. It was noted that walls in the CS area are grade A listed and so must be reinstated as is.
    • AM noted the meeting’s consideration of complete bans on traffic on CS. Sizes and weights of cherry-pickers that may be used in practice for inspecting and maintaining CS roofs were discussed. A 3-D model was suggested. He suggested that this is where negotiations over parking, loading, traffic restrictions should begin, rather than end.
    • DW emphasised that TT consulted in summer 2018, noted that strong concerns were raised about CS, met residents to discuss these concerns and hence gone to TAPOG with recommendations resulting from meeting residents.
  • JM asked about the conversion of Ocean Drive junctions from roundabouts to signalised junctions, hence preventing cars making U-turns. DW and RL responded that this issue will be resolved, potentially by the capital roads team removing the central reservation from Ocean Drive when it is resurfaced, and asked for time to go through processes.
  • A Hardie asked about coherence of design, specifically [adverts on] bus shelters, which may enhance TN’s image.
    • DW responded that TT has to perform a ‘massive’ comms task, which would involve the eventual contractors. Work on this is in progress but because the contractor has not yet been selected, this comms task can’t be started yet.
    • RL added that Hannah Ross is co-ordinating matters at senior levels in CEC.
  • The quantum of small business supporthas been signed off by TN’s board, despite low response rates to consultation.
  • Concerning other developments around Western Harbour, the contact is development@edinburgh.gov.uk.
  • TN now involves 127 building-fixing agreements, This will not involve 127 fixings, because there may be more than 1 person per building or group of buildings. Of the 127, currently only 11 are outstanding.

3 Date of next meeting

21 February 2019 (Subsequent meetings are to be agreed.)

Community Councils Together on Trams: Minutes of meeting held on Thursday 10 January 2019

Leith Links Community Council is a member of ‘Community Councils Together on Trams’ alongside Leith Central Community Council, Leith Harbour & Newhaven Community Council and New Town & Broughton Community Council. CCTT is the coalition of Community Councils who meet regularly to discuss, scrutinise and influence the intended continuation of the Edinburgh Tram system to Newhaven.


Abbreviations

BAFO = best and final offer LW = Leith Walk
CCTT = Community Councils Together on Trams NTBCC = New Town & Broughton Community Council
CEC = City of Edinburgh Council OBC = outline business case
CPZ = controlled parking zone POLHA = Port of Leith Housing Association
CS = Constitution St SPC = swept-path contract
ECI = early contractor involvement TAPOG = CEC’s tram all-party oversight group
EIA = environmental impact assessment TfE = Transport for Edinburgh
FBC = full business case TMRP = Traffic Management Review Panel
ISC = infrastructure and systems contract TN = Trams to Newhaven project
LCCC = Leith Central Community Council TRO = traffic regulation order
LHNCC = Leith Harbour & Newhaven Community Council TT = trams team
LLCC = Leith Links Community Council

1 Welcome, introductions

1.a Attendance

Charlotte Encombe CCTT/LCCC Andrew Mackenzie CCTT/LLCC
Hannah Ross TT/CEC Angus Hardie CCTT/ LLCC
Darren Wraight TT/CEC Rob Levick CCTT/LHNCC
Jennifer Marlborough CCTT/LHNCC Harald Tobermann CCTT/LCCC

1.a Apologies

Margaret Duffy CCTT/NTBCC Bruce Ryan CCTT minutes secretary
Rob Leech TT

2 Review of critical dates from CCTT

A Data Room will be open to councillors. Final Business Case (FBC) plus supporting documentation will be available to all the councillors in the data room. Procurements process is already complete but not published. Councillors will scrutinise procurement through the Finance & Resources Committee in early March but any decision will be subject to Full Council approval of the FBC.

The FBC will be considered by the Transport & Environment Committee on 28 Feb 2019 wherein councillors may speak and CCs can have a delegation. FBC will be made available to the Press on 22 Feb. On 14 March full council meeting, motions can still be tabled; this may cause postponements or amendments. Political briefings will take place prior this, i.e. presentations, explaining the business case, each party briefed separately and independent councillors separately by CEC.

If the FBC is approved the Council will not award contracts until after a procurement “standstill” period meaning contracts would be signed at the end of March. After contract signing there will be a 5 month Early Contractor Involvement (ECI) stage during which time CCTT will be able to liaise with contractor.

JM was assured that Brexit should not have any effect on the tram construction (other than general confusion).

HR explained to AH that the Hardie inquiry is completely independent from CEC so they have no access. Also the main subject is TIE rather than CEC. However, HR noted that CEC have followed the inquiry throughout and as far as possible have included/are including lessons learned. Whenever Hardie publishes his report CEC will endeavour to learn from that as well.

2.a Identify opportunities for further CCTT input at various stages.

HR confirmed that CEC are following the Government Green Book Guidance in finalising the FBC and in doing so seeking to demonstrate that the project stands up in terms of costs and benefits. HR asks if there anything that CCTT would like to see in the FBC. HT: we see them all as quite important and would like to see them all incorporated into the FBC (refer to update programme/issues list inserted at end of minutes as Appendix)

AM: will FBC be specific about issues along the route? In particular Constitution Street? HR: It will probably be more general. There will be information on traffic and construction management . If there are additional problems we have had to allow in the cost plan for that. It’s also reflected in the risk, although these are all commercially sensitive details. The preferred contractor would talk more to the community. AM is still concerned that the detailed designs are still very vague with lots of areas of uncertainty. DW: disagrees, there are 2 options for Constitution St to approve. Discussion follows on how TT has approached the design process, in which DW mentions that TT ‘stands rigidly behind the current design’. HT mentions the possibility/example of changing speed limits for Constitution St. which would have an adverse effect on the tram system. The point made was that the worst case scenario from a construction cost has been reflected within the FBC. DW also mentions that changes in speed limits are not considered at all, just possible changes in hard landscaping.

JM: passes on enquiry about a resident who had a letter from CEC about wires being attached to her building. Causes confusion for residents. DW advises to ask the persons in question to get in touch with him, there is a legal team on hand to help. AM wants to know how many fixings will be attached to buildings along the tram line.

HT: proposes that CCTT should ideally look at the FBC as soon as possible once the data room opens. CCTT members need to lobby our councillors for political inputs.

2.b Update from CCTT

JM’s note was provided through the design consultation and will be closed out through this process. CCTT will be able to express views through forum however consultation is now closed.

3 Update from CCTT

See above.

4 Other items

4.a Review of traffic

In email of 27 Nov 2018 Cllr Munro requested from CEC a review of traffic volume, access and egress and parking at Ocean Terminal. This request ended up with TT as CEC did not have such information. TT has not done any specific modelling in that area because the junction is not being altered for the benefit of the tram.

RL: this letter came from a discussion at LHNCC about traffic impact around western Harbor, where we are going to have building of school, properties etc. in the next 5 years. There are difficulties in Newhaven place, the coaches service the cruise harbor; a number of major projects taking place in a restricted area. LHNCC wants to flag up these potential difficulties, the effect on traffic, which is difficult already. It could turn into a mess that cannot be fixed. DW Tram team has not done any modeling on that junction and suggests that RL gets in contact with the transport planner for that area.

A comment was made about speeding vehicles along Ocean Drive. DW has agreed to arrange a meeting with Cllr Booth and provide him with a response from a tram perspective. DW will also report the problems with noise at night to the technical work group that he attends.

 

4.b List of interdependent programmes and who is responsible

Refer to document

4.b.1 Additional comments:

CE: how could a member of the public challenge any traffic management plans? In the case of the Abbeyhill rotary, it virtually appeared overnight and there was no way for members of the public to challenge that decision. DW: communications are so critical to this project. The Contractor is contractually bound to provide a stakeholder management resource which will be defined at the ECI period. They will give ample notice of any changes in traffic management during construction. Traffic management can be a standing agenda item in future community engagement forums. HT: it will be necessary to have a number of people on the street dealing with issues as they arise. DW: TT acknowledge this and confirm that a strategy will be further developed through the ECI period.

JM: Who is going to manage construction vehicles in the dock area and construction vehicles for other construction projects? DW: There is the Dock Area Working Group to deal with this. On it are Cala Homes, S1 homes, Harrisons, Leith Distillery, Ocean Terminal and Forth Ports, chaired by DW. DW is happy to circulate a list of the various groups, their remits, members and lines of communication.

In HT’s opinion the Supplementary projects list of 10 is far more important to the users of this community than the tram itself. He notes that the construction of the tram is necessarily the most important thing to the tram team, but the above list of issues should be resolved as well as it will be this community that will have to live with the consequences. Every single item on the list should be resolved; should have been resolved a long time ago, and the council needs to get its act together.

5 Quantification of environmental benefits for CC areas impacted by tram corridor: before/during/after.

Could be part of our political case still to be made to make sure that there are some. HT to keep trying to get hold of any data.

6 Next meeting 31 January and 21 February 5.30-7.30pm

RL and DW can be there all or just for some of the time. HR offers to provide answers to any specific queries you may have. DW is also happy to answer specific questions. Next meetings might be split into two parts: first part CCTT with TT for further clarifications and updates; second part for CCTT steering group only to plan best engagement with councillors, media and the wider public.

Community Councils Together on Trams: Minutes of meeting held on Thursday 29 November 2018

Leith Links Community Council is a member of ‘Community Councils Together on Trams’ alongside Leith Central Community Council, Leith Harbour & Newhaven Community Council and New Town & Broughton Community Council. CCTT is the coalition of Community Councils who meet regularly to discuss, scrutinise and influence the intended continuation of the Edinburgh Tram system to Newhaven.

 

The minutes of their most recent meeting, held on Thursday 29 November 2018 at 17:30 in Leith Community Centre were recently published and have been reproduced below for your information.

 


Abbreviations

BAFO = best and final offer LLCC = Leith Links Community Council
CCTT = Community Councils Together on Trams LW = Leith Walk
CEC = City of Edinburgh Council NTBCC = New Town & Broughton Community Council
CPZ = controlled parking zone OBC = outline business case
CS = Constitution St POLHA = Port of Leith Housing Association
ECI = early contractor involvement SPC = swept-path contract
EIA = environmental impact assessment TAPOG = CEC’s tram all-party oversight group
FBC = full business case TfE = Transport for Edinburgh
ISC = infrastructure and systems contract TN = Trams to Newhaven project
LCCC = Leith Central Community Council TRO = traffic regulation order
LHNCC = Leith Harbour & Newhaven Community Council TT = trams team

1 Welcome, introductions

1.a Attendance

Charlotte Encombe CCTT/LCCC Andrew Mackenzie CCTT/LL CC
Rob Leech TT/TN project director (Anturas Consulting) Carol Nimmo CCTT/NTBCC
Rob Levick CCTT/LHNCC Bruce Ryan CCTT minutes secretary
Jennifer Marlborough CCTT/LHNCC Harald Tobermann CCTT/LCCC

1.a Apologies

Margaret Duffy CCTT/NTBCC Sally Millar CCTT/LL CC
Angus Hardie CCTT/LL CC Darren Wraight TT/CEC

2 Update from CCTT

A Mackenzie reported that some CS residents met with their CEC councillors, D Wraight and 3 members of LLCC. This meeting was about the design options from the Foot of the Walk to Queen Charlotte St. It was also to ensure that the CEC councillors were aware of the CS residents’ views. AM also stated that meeting was useful, but the CS residents’ issues remain in need of further consideration.

H Tobermann reported that the CCTT steering group will soon compile a list of outstanding issues along the route, and share that with TT asap.

  • This list may be ranked by importance to CCTT.
  • It was noted that J Marlborough has complied such a list for LHNCC’s area, of the format.
Design Drawing Issues
  • The list will be accompanied by a request for information on how TT intends to solve the issues.
  • Action: H Tobermann to circulate a template to the four CCs. CCs to supply their issues so that HT can submit its list by 12 December.

It was noted that LCCC has ratified CCTT’s submission to the second trams consultation, and that NTBCC has also sent in its own submission.

3 Update from Tram Team

R Leech reported that his colleagues Hannah and Steve gave a presentation to the Edinburgh Association of Community Councils. This presentation was high level, rather than detailed, concentrating on the question ‘why are we doing this?’ The response was mixed: some supporting the proposed project, others suggesting the money would be better spent on roads.

  • It was noted that EACC does not speak for LCCC and NTBCC.

3.a BAFO

R Leech reported that TT has received the BAFO tenders, and finalised their evaluation. This will go before the TN board on 3 December, with a recommendation to agree the pricing for the FBC, so that it is ready to go through board approval in January. This will be a formal committee process before the FBC is sent to CEC, but there will be no publicity around this.

The FBC will state how much of the £165 m budget would be spent on the ISC and the SPC. (The SPC costs are already known.) The budget also covers risk, inflation etc.)

3.b Consultation2: initial feedback

R Leech reported

  • The Support for Business (SFB) consultation has closed. Analysis will go before TAPOG on 12 December, with initial recommendations. These are generally positive but some elements of SFB proposals are clearly preferred over others.
  • Analysis of the design consultation is not yet finished. There were fewer respondents than for the first design consultation, but the feedback has been generally positive.

R Leech suggested bringing the SFB and design presentations that will be seen by TAPOG to the next CCTT/TT meeting, along with resulting actions.

H Tobermann suggested that businesses currently much uncertainty (e.g. from Brexit), that businesses in the relevant area will experience a major impact from [construction of] TN, and that current uncertainty is likely to be exacerbated by current lack of implementation detail in the SFB package. Hence CCTT will push hard for resources to finalise such details and hence minimise [TN-related] uncertainty.

  • R Leech responded that this would be worth exploring in the next CCTT/TT meeting. He added that the fine detail of the SFB will be worked out with the successful contractor.
  • H Tobermann reiterated the point in CCTT’s submission that the best way to think about such issues was to consider ‘life during construction’. R Leech concurred.
  • C Encombe added that the previous tram work had been ad-hoc and hence far more unpleasant than was necessary. She noted that LCCC now has a clean streets committee that is likely to ‘police’ LCCC’s area during construction.
  • R Leech stated that a report on the [SFB and design consultation] analyses will be shared with CCTT. He is not yet sure how analyses will be made public, but a ‘”you said, we did” + action plan’ publication is likely. He anticipated that this would cover some of the issues raised by CCTT.
  • R Leech suggested that the remaining issues will be around fine detail, e.g. ‘this loading bay doesn’t work’.

4 Outstanding design issues and permanent TROs post construction including:

The discussion moved from item 3b to item 4 without a noticeable break.

Items 4q to 4e in the agenda were not discussed in any detail because D Wraight was not present.

J Marlborough expressed concern that consultation 2 concentrated on Leith Walk, and did not fully cover LHNCC’s area. She suggested that respondent analysis is broken down by area.

  • R Leech responded that the majority of the changes in the plans in consultation 2 were in the centre of the route, but that consultation 2 covered all of the route.

R Leech stated that the design must be completely finalised by summer/early autumn 2019. He added that when the FBC is presented, the fundamentals of the design (e.g. the number of traffic and tram lanes) will be fixed. A need for fundamental changes would cause the project to halt. However, the detail in J Marlborough’s list is not fundamental and so can be carried forward to the next stage.

C Nimmo asked about NTBCC and local residents’ concerns, including the right turn from London Road onto LW.

  • R Leech responded that in his opinion, this turn would not work [during and after construction]. However, he acknowledged that a full explanation of this was needed, so such concerns should be included in CCTT’s list of outstanding issues.

C Nimmo stated that to the best of her knowledge traffic modelling has not been undertaken.

  • R Leech responded that it has been done in the past, but that CN may have heard that it is waiting to be updated.
  • Decision: It was agreed to add this to the list of CCTT concerns, for discussion at a meeting with NTBCC and residents.
  • Action: When TT receives CCTT’s list , TT will check the list for ‘fundamental’ issues

o R Leech added that non-fundamental issues can be covered by the risk and contingency budget lines.

  • H Tobermann requested a ‘first-pass’ response to CCTT’s list asap.

H Tobermann added that CCTT has compiled its own timeline of TN events..

  • Action: R Leech to send TT’s own timeline to CCTT, so that CCTT and TT are using the same timeline.

H Tobermann reported that some CEC officials do not know that TN is happening, or significant relevant dates.

  • R Leech responded that TN has a project board (including senior CEC officers from finance, procurement, legal, transport) chaired by the executive director of Place. The board is briefed on TN timetable at its monthly meetings. There is also a technical working group, including [representatives from] all CEC departments involved in the TN. They are also briefed on timescales and their own input to this. There are also ad-hoc meetings with various CEC departments. Hence if CEC officials appear to be unaware of TN, they are acting incorrectly in some way.
  • H Tobermann added that if relevant CEC officials are unaware, he fears for the supplementary projects and other projects that might clash with TN under their control. He emphasised that this lack of awareness was not TT’s fault.

J Marlborough asked whether the frequency of use of LW by emergency services has been taken into account, given that she sees such vehicles responding to emergencies whenever she visits LW. She added that the police use Constitution St regularly.

  • R Leech responded that TT has set up a traffic management review panel (including Lothian Buses, CEC, emergency services). It will meet regularly during construction. Emergency services will always have a clear route through construction. An in-progress part of the design process is considering how a clear route after construction. If an accident blocked the route, trams ‘up the line’ [and other traffic] would be stopped so that they didn’t cause further congestion.

R Leech stated that the TROs timeline is currently unknown.

  • This is because the TROs depend on feedback from CCTT and others.
  • D Wraight is assembling a note on the TRO process, considering statutory timescales, CEC needs etc.
  • This matter will be on a future CCTT/TT agenda.

4.a Design issues

See also appendix, item 8a.

R Leech stated

  • D Wraight is working on optimising bin locations etc. However, bins are CEC’s waste team’s responsibility, ultimately under the control of CEC’s director of place. Also, RL has a strong relationship with G Barwell, head of CEC’s waste division, who is very much alive to TN and working towards getting the bin situation right.
  • Work on bus-stop locations is in progress. This work considers the proposed 2-lane layout, pinch-points, bus trackers, signage etc. TT is ‘hooked in’ with J White, Lothian Buses’ operations manager. He has been working on traffic management plans and deigns. There is also a technical working group including Lothian Buses to finalise relevant parts of the design. This work will be completed over the next 2 months.
  • He is not currently sure of the progress towards solving TN-related parking issues. He is aware that Corstorphine is the CEC area that will first be promoted into a CPZ, and that Leith will be second, but has no power to influence this.

o H Tobermann was unconvinced that Corstorphine should be first, considering it is not having a tramline installed.

4.b Extract from Tram Design Manual

See appendix, item 8b.

H Tobermann asked whether this edition of the manual is current. R Leech stated that the principles are but this version has been superseded because street guidance has moved on very much in 13 years.

H Tobermann then asked what standards TT is working to, to which R Leech replied that there were very many.

Action: R Leech to supply details of guidance currently used by TT (This info is to come from Atkins.)

5 Review and update of tram pre/construction programme

Action: as noted previously, R Leech to send TT’s timeline to CCTT

R Leech confirmed that BAFO tenders arrived on 16 November, and that the relevant board meeting is on 3 December.

H Tobermann reported that he regularly checks whether Lord Hardie is due to publish his report on the issues in the initial Edinburgh tram construction, that he has found thorugh FOI that the cost of the enquiry is likely to soon exceed £10 m, and that it is highly desirable for the report to come out before TN gets too far.

6 Next meeting (10 January 2019)

6.a to agree: main topic: quantification of environmental benefits for area along tram corridor: before, during and after tram project

R Leech asked for clarification of the question CCTT is asking about the environmental aspects of TN.

  • H Tobermann responded that CCTT feels it does not have sufficient information from the TT, and that the existing environmental impact assessment (EIA) is from 2006, i.e. out of date. Hence it needs to be updated to reflect what is going to be built in 2019-2022.
  • That is CCTT wishes robust assurance that TN will provide a net environmental benefit from the start of construction until some years into its running life. He suggested that traffic modelling could aid such calculations.
  • There was discussion of the difficulty and various methods of proving environmental effects, e.g. effect of the new housing to be built in Leith, working from current car numbers, types and pollution levels.
  • R Leech reminded the meeting that he must follow the Tram Act’s requirements.
  • B Ryan asked whether the Act precluded an up-to-date full EIA being undertaken.

Action: H Tobermann to supply to TT detail of what is sought, including information on CEC’s LEZ staff; R Leech to respond to this

Action: main subject of next meeting to be the ‘you said, we did’. (See item 3b, bullet point 6 above.)

6.b to agree: (proxy) evidence to share in advance of the January meeting

Carried forward to a future meeting when environmental benefits are discussed

6.c to note: minute taker in January

Action: C Encombe to take this meeting’s minutes

7 AOCB

H Tobermann mentioned an email from Michael Motion of Turner Townsend, inviting CCTT to a meeting on 11 December (2pm to 6pm, venue TBC) about the Foot of the Walk to Ocean Terminal cycle way feasibility study. Action: HT to circulate this invitation.

  • R Leech stated that the meeting is to agree the objectives and scope of this project. He added that AECOM has been appointed to undertake a ‘route-optioneering’ exercise. There will then be a public consultation to sift options.

It was noted that Rory Garriock is now undertaking TN analysis and planning work, rather than being TT’s public face.

People who wish to contact TN/TT should email tramstonewhaven@edinburgh.gov.uk. This address is monitored daily.

8 Appendix

8.a Extract from CCTT response to consultation 2

Design issues: while many of the initial concerns have been resolved with the current designs, more detailed design work is required

  • in a few locations (especially at Ocean Drive, Constitution Street south; Shrub Place, Picardy Place)
  • optimising communal bin locations
  • refining bus stops/bays/shelters locations and dimensions
  • resolving issues around pavement/cycling/bus stop interactions at a number of locations
  • parking/loading locations (including side streets).

CCTT believes that this can be achieved in the available time, but such detailing may require additional design resources and a sincere engagement with the people most affected.

8.b Extract from Tram Design Manual 2005

A Commensurate Quality of Townscape and Public Realm Design

2.9 The proposed tram system is important not only as a new public transport project but also, as a strategic piece of new development, to act as an important catalyst and promote quality design within the townscape and public realm of the city.

2.10 Partnership working will be needed to ensure that an appropriate strategy for Edinburgh’s wider public realm can be put in place to complement works undertaken as part of the tram project. Fitting the tram route and its alignment into the townscape is the first stage of the design process. An understanding of the urban design issues that apply to a section of the tram route or a specific space along the route are required in order to achieve quality of design. This wider townscape assessment is essential in order for the tram to fit comfortably within a wider public realm and to realise the opportunity to improve the quality of streets and public spaces to a level commensurate with the quality of the city’s built heritage.

2.11 In order to ensure that a piecemeal approach is avoided, a joint programme of public realm works must be drawn up by the Council with input from key stakeholders, in tandem with the proposed tram implementation programme. This is essential to minimise disruption on site and to minimise abortive works.

 

 

Leith Links Community Council, Next meeting Monday, 26th November

The next meeting of Leith Links Community Council will be on Monday, 26th November, in Leith Community Centre (Shore Room). Please remember the new start time is 6.30pm.

If you live in the Leith Links area, and have questions or concerns to discuss, we would be pleased to welcome you.

LLCC Minutes Draft October 2018

Draft Agenda 26.11.18

 

 

 

 

 

 

Leith Links Community Council Meeting, Monday 29.10.18, 6:30pm, Leith Community Centre

The next meeting of Leith Links Community Council will be on Monday, 29th October, in Leith Community Centre (Shore Room). Please remember the new start time is 6.30pm.

If you live in the Leith Links area, and have questions or concerns to discuss, we would be pleased to welcome you.

Agenda Monday 29.10.18

Draft Minutes Monday 25 September 2018

All previous Minutes are available here

 

LEITH LINKS CC, NEXT MEETING IS MONDAY 27 NOVEMBER, 7pm

Your Community Council

The next meeting of the Leith Links Community Council will be on Monday 27 November, at 7 pm in the Shore Room, Leith Community Education Centre, New Kirkgate  All interested local people are very welcome.

Minutes October 2017 (draft until adopted)   Agenda November 2017

Also  – did you know you can go and talk to one of your local Councillors, if you have a private matter you need to discuss (just turn up, no need to ‘book’):

  • Councillor Chas. Booth (Scottish Green) Termtime Tuesdays 5:30 – 6:30 Leith Library , Ferry Road.
  • Councillor Adam McVey (SNP) 3rd Wednesday of month, 6pm Leith Library, Ferry Road.
  • Councillor Gordon Munro (Scottish Labour) 1st & 3rd Mondays of month 6:30 – 7:15 Leith Community Education Centre, New Kirkgate